NancyAndFred.Com

[ HOME ] [ OUR ZOO ] [ OUR PROJECTS ]


Our Projects

Laundry
Master Bedroom
Kitchen & Dining
Master Wing
Master Bath
Sun Porch
Barn
Shed
Bridge

Laurel Lake
First Porch
Current Porch

Bridge

The Sad History

This little task in August 2002 was unplanned and unexpected until Mother Nature displayed her prowess in May. Our original bridge was built in 1973 after buying an acre and a half across the creek from Pat Bulman. The main supports were four 20 foot long 6x7 rough cut spruce beams, purchased from Joe Bayan(Sp?) who had a small saw mill just over the state line on rte 267. The decking was rough sawn 2x8, also from Joe. I think the total cost was about $300 - delivered to the back yard! Before putting it in place, all the lumber received a coat of some hazardous as all get out wood treatment applied with a brush. It killed all the grass where the stuff was being applied.

At that time the creek was about 14-16 feet wide, bank top to bank top but on the far side the bank sloped at about a 60 degree angle. To reduce the effective width a three sided box, 12 foot along the bank and out about 8 foot, was constructed on the far side of logs (cut from Schoonover's land on top of Echo). This was then filled with rocks - taken from our garden, that's some kind of a commentary in itself! The ends of the main beams then reached from about a foot onto the bank past the end of the box on the far side and about 4 feet onto the bank on the house side. In the early years of the bridge it seemed I spent half my time trying to keep it from being washed away. The log box held well but the house side kept getting eroded, partially because I found out where the previous residents had dumped the ashes from their coal furnace. Ashes wash away real easily once exposed.

Although the log box held up very well, it was subject to being under cut. This was corrected with more rocks and many bags of Sakrete. One year in the early '80s the creek nearly made it over the bank and the bridge was hanging by two of the four mains. The other two ended in space. To repair that, jack posts were concreted in the creek bed under the danglers. Those were then used as a start to effectively build another box on the house side. Double 2x12s (treated) were placed perpendicular to the mains and an addition was made to the bridge on the house side making the overall bridge now 26 feet long. This extension seemed to do the trick. In the 90s the condition of the original lumber was deteriorated so the original decking was removed, doubled 2x12s were added from the jack post location to the far side and new pressure treated decking was put down. Now it even looked like a bridge.

On May 28th, 2002 we got 3 1/2 inches of rain in about 20 minutes. Say Goodbye! Standing in the kitchen looking out at the rain and watching one's bridge become a boat is a very memorable experience. I'd have to say I knew there was going to be a problem when Jennings' bridge floated by. All told, that storm took out four bridges, Demske, Jennings, Howey and Bulman. The Lauffer/Crittenden bridge was the only one to survive and that got moved and nearly cut out on the road side.

before2.JPG

This picture was taken near the end of the storm just after the worst was over. The small tree at the left was about 3 feet from the bridge - 10 minutes earlier.


before1.JPG




A few hours earlier this photo would have looked right across the bridge. Now it looks right across where the bridge used to rest on the log box.

The Replacement

Preparation for this job involved putting the creek back and removing the remains of the old bridge and its supports. I say "putting the creek back" because it had cut new channels and partially or completely filled in the old channel. This was accomplished by Daniels Back hoe Service of Vestal (785-5009) using an excavator and a back hoe. They did a great job at a very reasonable price - highly recommended. They also lifted one end of the two large truss joists across the creek saving me a lot of heavy labor.

The underpinnings are 3 steel trusses, two of which are 32 foot long and 18 inches high. The third truss is actually a pair of 20 footers, 14 inches high, welded into one by Ed Meyers (thanks, Ed). They were dug in to leave the tops about 4 inches above ground on the house side and 8 inches on the other side. These trusses held the water walls of our above ground pool together at the top and were saved when the pool was removed several years ago. Good thing! Even at 32 feet long they only go about 5' back from the bank on each side. Before the back hoe work, they wouldn't really have reached.

half floored.JPG

On August 8th, the floor is partly down. This shows the steel beams and the 2x4 bolted to them to fasten the flooring. The outer two beams each have one more section of 2x4 to be bolted on.


shows creek.JPG

Taken at the same time, this is a side view of the trusses and shows how the creek was dug back out. It's much the same as it was before except for the missing vegetation on the banks...and a few bridges. Notice the darn thing is dry except for a one gallon size pool under the bridge.

Pressure treated 2x4s were drilled and bolted to the top of the trusses (3/8x4 bolts) which conveniently have 2 L-shaped steel members with about 1/2 inch between them on both top and bottom. The flooring - PT 2x8x8', 50 of them plus 5 2x8x10' - is then fastened to the 2x4s with deck screws. A short ramp was made on each end to allow the tractors to be driven across.

staining.JPG

Here we have the painter-in-chief, with one of her supervisors, applying stain. The flooring is down and the railing largely finished.

A railing was made that is supported by a 3 sided box of vertical 2x6s fastened to the sides of the 2x8x10 floor boards. Additional 2x8x10s were bolted to the bottom of the two outer trusses and the vertical 2x6s are also fastened there to provide stiffness. This is finished by a pair of 2x6s at right angles fastened one on top and one to the inside surface of the verticals. Nancy stained the entire bridge to match the barn and shed. A lot of work but it really gives a great appearance. The electrical supply to the shed and barn, which runs along under the bridge, was replaced, but this time from the sub panel in the shop rather than from the house. Breakaway connections were made at each end of the bridge again, but let's hope they're never needed.

Trivia

The bridge has supported a 3000 pound load of gravel being pulled by the garden tractor with no visible flinching. It was started on August 6 and was walkable on August 9. It was completely finished on August 16. The day time temps during this period were in the upper 80s and low 90s. At the time of completion it was 86" from the bottom of the steel to the creek bed in the middle of the bridge. In August 2003 that dimension had decreased to 80" due to silting in the creek bed. The total cost was about $1200. This does not include the trusses which we had, the back hoe service which needed doing anyway, nor my labor... but I work cheap.

finished.JPG

The Finished Product